All of the following are types of demand EXCEPT
答案解析
解析:
1. Customer Orders
2. Sales forecast
3. Production requirements
4. Interplant orders
5. Spares demand
6. Stockpiling for peak periods
7. Promotional requirements
8. Safety stock level changes
相关题目
An ATO company produces subassemblies based on actual customer orders, and stocks the most commonly sold configurations. Planning occurs on a weekly basis. Safety capacity would be used to
Which of the following information from MRP can be used to sequence production orders?
The relationship of all components at the same level in the BOM to be available at the same time is
A tool that enables a planner to perform bottom-up replanning is
Period 1 2 3 4 5 6 7 8
Gross requirements 40 10 30 50 50 20 30 40
Scheduled receipts
Projected available 130
order quantity: 40
Safety stock: 10
Lead time: 3 periods
What are the net requirements for period 7?
Which of the following types of orders remain unchanged during a MRP run?
Period 1 2 3 4 5 6 7 8
Gross requirements 40 40 50 60 60 80 80 80
Scheduled receipts 100
Projected available 60
order quantity: fixed order qty of 100
Safety stock: 10
Lead time: 2 weeks
The scheduled receipt in the information provided represents a purchase order. MPR would recommend
2 defective inexpensive parts are discovered in a sample during incoming inspection but the lot itself is accepted. The defective parts are
Which of the following statements is true of forecast demand in the MPS as it relates to MRP?
A company has lean relationship with a supplier, a communication technique beneficial for communicating to the supplier for procurement planning over the horizon is a