When Mean Average Deviation equals 225 and the sum of the actuals is 2,600 across 10 periods. What is the standard deviation using the simple math method?
答案解析
解析:
The sum of the actuals is a number that is not needed for this problem
相关题目
The volume/mix of throughput on which overhead absorption rates are established is
A problem of considering reducing rated capacity in order to allow for safety capacity is
Material produced as a residual of or incidental to the production process is a
Efficiency is defined as
An ATO company produces subassemblies based on actual customer orders, and stocks the most commonly sold configurations. Planning occurs on a weekly basis. Safety capacity would be used to
Which of the following information from MRP can be used to sequence production orders?
The relationship of all components at the same level in the BOM to be available at the same time is
A tool that enables a planner to perform bottom-up replanning is
Period 1 2 3 4 5 6 7 8
Gross requirements 40 10 30 50 50 20 30 40
Scheduled receipts
Projected available 130
order quantity: 40
Safety stock: 10
Lead time: 3 periods
What are the net requirements for period 7?
Which of the following types of orders remain unchanged during a MRP run?