A "order to be released" would be what type of MRP Message?

A
Action Message
B
Order Message
C
Manufacturing message
D
Exception Message

答案解析

正确答案:A

解析:

MRP has two types of messages Action and Exception messages. An "Order to be
released" message would be considered an action message. Manufacturing and order messages are
not MRP messages.
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

A textile plant spins fiber into yarn, weaves yarn into a line of standard fabrics, and dyes these fabrics to custom-color specifications. Dyeing is done in a light-to-dark sequence to reduce high changeover costs. While spinning and dyeing capacity is adequate during the peak season, the capacity of the plant's weaving operations is well below the required level. If product design and price are the primary competitive factors, which two of the following actions would effectively resolve the problem?
1. Building inventory of feed yarn just before the peak season begins;
2. Building inventory of undyed fabric just before the peak season begins;
3. Changing weaving and dyeing schedules to accommodate the needs of key customers
4. Changing weaving schedules to use subcontractors during the peak season;

单选题

CRP directly interfaces with

单选题

The most appropriate way to increase the capacity available for one day on a production line is to

单选题

The maximum output capabilities of a resource is known as

单选题

A new product has been introduced and has a fairly stable production schedule. Which of the following actions is the best use of CRP?

单选题

A MTO company produces a standard product sold through their own warehouses. Which of the follow CRP techniques would most likely be used to validate the material plan?

单选题

The primary output of the CRP process is

单选题

Using suppliers to perform subcontracted operations requires that the services performed

单选题

A scheduling technique effective for scheduling where several bottleneck stages may exist is

单选题

The ratio of hours work to the hours available is

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码