Using a family tree subdivision of effort, and starting with the end objective required and successively subdividing it into manageable components in terms of size and complexity is called the:

A
resource breakdown structure
B
project task list
C
work breakdown structure
D
Gantt chart

答案解析

正确答案:C

解析:

As defined by NASA, the Work Breakdown Structure is a family tree subdivision of effort required to achieve an objective. The WBS is developed by starting with the end objective required and successively subdividing it into manageable components in terms of size and complexity, such as program, project, system, subsystems, components, tasks, subtasks and work elements. It should be product or task oriented and should include all the necessary effort which must be undertaken to achieve the end objective.
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码