Which of the following should be considered during the production planning process?
I. Component requirements
II. Capacity availability
III. Manufacturing labor needs

A
I and II
B
I and III
C
II and III
D
I, II, and III

答案解析

正确答案:C

解析:

In production planning, component availability would not be determined, as MRP would handle this. However, capacity would be checked at a rough cut level and manufacturing labor needs could be determined. Component availability might be checked at the production planning level if it were a scarce component.