Which of the following statements are true regarding super bills?
I. It is at the top level of the product structure.
II. It groups components based on work centers.
III. It aggregates components into modules.
IV. It groups small parts into kits.
答案解析
解析:
Supper Bill of Material:
A type of planning bill, located at the top level in the structure, that ties together various modular bills (and possibly a common parts bill) to define an entire product or product family. The quantity per relationship of the super bill to its modules represents the forecasted percentage of demand of each module. The master-scheduled quantities of the super bill explode to create requirements for the modules that also are master scheduled. See: pseudo bill of material.
相关题目
Which of the following actions invalidates acceptance sampling for purchased items?
Which of the following environments is most unlike the others from an operational perspective?
Records for a part dimension over time show it has a single mean and that values tend to cluster around the mean. This type of distribution is likely to be referred to as
Which of the following data collection points serves 2 purposes in a pull environment that has machining and assembly lines and receives material directly to point-of-use areas?
A downsized associated with linking corporate financial incentives to specific performance objectives is that
W/proper lot sizing, operation overlapping will
Standard activities producing differing results is an example of
Backward scheduling work center A
Move time between operations = 1 day
Wait time = 1 day
Due date is day 100
Operation Work center Operation time Queue time
10 A 2 5
20 B 4 3
30 C 2 1
A characteristic of a lean enterprise strategy is
If a point is outside of the upper control limit, which of the following statements is most applicable to the process?