In a distribution requirements planning system, in-transit lead time is accounted for by:

A
safety stock in the receiving warehouse.
B
being offset as a gross requirement in the supply warehouse.
C
safety stock in the supply warehouse.
D
None of the above

答案解析

正确答案:B

解析:

In DRP, the lead time between warehouses is offset as the planned shipment to the receiving warehouse becomes the gross requirement in the supply warehouse. This logic is similar to the lead-time offset in an MRP system where the planned order release is offset by the lead time to purchase or make the part.
题目纠错
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码