素桩成孔及浇筑过程中质量控制关键点说法错误的有()
A
初凝时间不应小于45h
B
混凝土灌注至设计桩顶标高以上0.80m
C
终孔后需报监理组织终孔验收
D
软切割时需使用超缓凝混凝土
E
硬切割时素桩宜选用普通商品混凝土
答案解析
正确答案:AB
解析:
素桩成孔及浇筑过程中质量控制关键点说法错误的有
A. 初凝时间不应小于45h
B. 混凝土灌注至设计桩顶标高以上0.80m
C. 终孔后需报监理组织终孔验收
D. 软切割时需使用超缓凝混凝土
E. 硬切割时素桩宜选用普通商品混凝土
答案: AB
Explanation: The correct statements are C, D, and E.
C: After the completion of the hole, it is necessary to report to the supervision organization for final hole acceptance.
D: Soft cutting requires the use of super slow-setting concrete.
E: For hard cutting, ordinary commercial concrete is suitable for the cast-in-place pile.
The incorrect statements are A and B:
A: The initial setting time of concrete should not be less than 45 hours, which is an incorrect statement.
B: The concrete should be poured to a height of 0.80m above the design pile top level, which is also incorrect.