素桩成孔及浇筑过程中质量控制关键点说法错误的有()

A
初凝时间不应小于45h
B
混凝土灌注至设计桩顶标高以上0.80m
C
终孔后需报监理组织终孔验收
D
软切割时需使用超缓凝混凝土
E
硬切割时素桩宜选用普通商品混凝土

答案解析

正确答案:AB

解析:

素桩成孔及浇筑过程中质量控制关键点说法错误的有 A. 初凝时间不应小于45h B. 混凝土灌注至设计桩顶标高以上0.80m C. 终孔后需报监理组织终孔验收 D. 软切割时需使用超缓凝混凝土 E. 硬切割时素桩宜选用普通商品混凝土 答案: AB Explanation: The correct statements are C, D, and E. C: After the completion of the hole, it is necessary to report to the supervision organization for final hole acceptance. D: Soft cutting requires the use of super slow-setting concrete. E: For hard cutting, ordinary commercial concrete is suitable for the cast-in-place pile. The incorrect statements are A and B: A: The initial setting time of concrete should not be less than 45 hours, which is an incorrect statement. B: The concrete should be poured to a height of 0.80m above the design pile top level, which is also incorrect.
口袋书题库2.0版练习

扫码进入小程序
随时随地练习

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码